Back to projects

Brook Street Storm Sewer Upgrades and Reconstruction

Channel-Port aux Basques, Newfoundland and Labrador

completeWastewaterRNIS
Federal contribution
$235,840
Federal share33%

of $707.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Rural & Northern Infrastructure Stream
Construction start
May 9, 2023(actual)
Construction end
Nov 15, 2023(actual)

Also in Channel-Port aux Basques

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61199 in the federal list. How to read these figures.