Charlottetown Eastern Gateway - Water and Sewer Rehabilitation

Charlottetown, Prince Edward Island

completeWastewaterGIS
Federal contribution
$1.3M
$1,320,000
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built
Program
Green Infrastructure Stream
Ultimate recipient
City of Charlottetown
Construction start
Dec 5, 2022(actual)
Construction end
Nov 12, 2024(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Dec 31, 2024

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61288 in the federal list. How to read these figures.