Charlottetown Eastern Gateway - Water and Sewer Rehabilitation
Charlottetown, Prince Edward Island
Federal contribution
$1.3M
$1,320,000
Federal share40%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Charlottetown
- Construction start
- Dec 5, 2022(actual)
- Construction end
- Nov 12, 2024(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Dec 31, 2024