Stratford - New Water Reservoir
Stratford, Prince Edward Island
Federal contribution
$320,276
Federal share40%
of $800.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 1, 2022
2022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stratford
- Construction start
- Sep 13, 2023(actual)
- Construction end
- Dec 3, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast May 22, 2023
- Construction end5 months lateforecast Jun 28, 2024