Stratford - New Water Reservoir

Stratford, Prince Edward Island

completeDrinking WaterGIS
Federal contribution
$320,276
Federal share40%

of $800.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2022
2022202320242025
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Stratford
Construction start
Sep 13, 2023(actual)
Construction end
Dec 3, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast May 22, 2023
  • Construction end5 months lateforecast Jun 28, 2024