Codiac Transpo - Fleet Renewal
Federal contribution
$900,649
Federal share35%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
202220232024
Built
Approved 3 years before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Jul 20, 2023(actual)
- Construction end
- Apr 28, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2023
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61329 in the federal list. How to read these figures.