Centre Jean-Daigle – Solar Panels

Edmundston, New Brunswick

underwayGreen EnergyGIS
Federal contribution
$3.2M
$3,220,000
Federal share40%

of $8.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2022
today
20222023202420252026
BuiltForecast

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Edmundston
Construction start
May 23, 2023(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start6 weeks earlyforecast Jul 3, 2023

Also in Edmundston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61393 in the federal list. How to read these figures.