Replacement of culverts at Edgar Creek
Federal contribution
$1.4M
$1,350,000
Federal share50%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 22, 2017
2017201820192020
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Edmundston
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Nov 30, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2016
- Construction end4 weeks lateforecast Oct 31, 2019
Also in Edmundston
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48228 in the federal list. How to read these figures.