Minoru Place Activity Centre Conversion to Arts Centre
Federal contribution
$133,000
Federal share4%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
2023
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Richmond
- Construction start
- Oct 11, 2022(actual)
- Construction end
- Oct 16, 2023(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Nov 30, 2023
Also in Richmond
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61426 in the federal list. How to read these figures.