Eastern Gateway - Storm Water Planning

Charlottetown, Prince Edward Island

completeCapacity BuildingGIS
Federal contribution
$44,000
Federal share40%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2022
202220232024
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Charlottetown
Construction start
Nov 1, 2021(actual)
Construction end
Jan 12, 2024(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Dec 29, 2023

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61444 in the federal list. How to read these figures.