Charlottetown Eastern Gateway - Storm Water Management

Charlottetown, Prince Edward Island

completeWastewaterGIS
Federal contribution
$2.3M
$2,270,433
Federal share14%

of $16.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2022
202220232024
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Charlottetown
Construction start
Nov 6, 2023(actual)
Construction end
Nov 12, 2024(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Dec 4, 2023
  • Construction end7 weeks earlyforecast Dec 31, 2024

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61445 in the federal list. How to read these figures.