Kelly's Pond Watershed Restoration
Stratford, Prince Edward Island
Federal contribution
$138,600
Federal share40%
of $346.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 1, 2022
202220232024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stratford
- Construction start
- Jul 23, 2023(actual)
- Construction end
- Oct 31, 2024(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2024
Also in Stratford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61453 in the federal list. How to read these figures.