Kelly's Pond Watershed Restoration

Stratford, Prince Edward Island

completeDisaster MitigationGIS
Federal contribution
$138,600
Federal share40%

of $346.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2022
202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Stratford
Construction start
Jul 23, 2023(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2024