Vehicle Acquisition (Phase 7)

Undefined, British Columbia

completePublic TransitPTIS
Federal contribution
$6.0M
$6,005,732
Federal share40%

of $15.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 27, 2022
2022
Built

Approved 10 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
British Columbia Transit
Construction start
Oct 15, 2021(actual)
Construction end
Jul 31, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Sep 1, 2021
  • Construction end8 months earlyforecast Mar 31, 2023