Back to projects

Confederation Building East Block Elevator Refurbishment

St. John's, Newfoundland and Labrador

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$1.6M
$1,560,000
Federal share80%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 28, 2025
20222023202420252026
Built

Approved 3.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 1, 2023(actual)
Construction end
Mar 15, 2026(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jan 9, 2023
  • Construction end2 weeks earlyforecast Mar 31, 2026

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61464 in the federal list. How to read these figures.