Kent - District of Kent Aquatic Centre
Federal contribution
$454,112
Federal share3%
of $13.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
today
20222023202420252026
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- District Municipality of Kent
- Construction start
- Jul 29, 2024(actual)
- Construction end
- Sep 15, 2026(forecast)
Against the original forecast
- Construction start2 months lateforecast May 15, 2024
Also in Kent
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61485 in the federal list. How to read these figures.