Agassiz Avenue Infrastructure Improvements
Federal contribution
$652,500
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District Municipality of Kent
- Construction start
- Mar 31, 2017(actual)
- Construction end
- Jan 31, 2018(actual)
Against the original forecast
- Construction start8 weeks earlyforecast May 29, 2017
- Construction end4 months lateforecast Oct 6, 2017
Also in Kent
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47685 in the federal list. How to read these figures.