Agassiz Avenue Infrastructure Improvements

Kent, British Columbia

completeDrinking WaterCWWF
Federal contribution
$652,500
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Mar 31, 2017(actual)
Construction end
Jan 31, 2018(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 29, 2017
  • Construction end4 months lateforecast Oct 6, 2017

Also in Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47685 in the federal list. How to read these figures.