Back to projects

Air Handling Unit Retrofit at Health Sciences Centre

St. John's, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$800,000
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
2022202320242025
Built

Approved 3.2 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 15, 2023(actual)
Construction end
Apr 30, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 1, 2023
  • Construction end11 months earlyforecast Mar 31, 2026

Also in St. John's