New Accessible Bus Shelters
St. John's, Newfoundland and Labrador
Federal contribution
$80,527
Federal share40%
of $201.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
202220232024
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Nov 24, 2022(actual)
- Construction end
- Mar 31, 2024(actual)
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61548 in the federal list. How to read these figures.