Capital - Maliview Wastewater Treatment Plant Upgrade
Salt Spring Island, British Columbia
Federal contribution
$1.1M
$1,105,000
Federal share50%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 22, 2022
today
202220232024202520262027
BuiltForecast
Approved 6 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Capital Regional District - Salt Spring Island Electoral Area
- Construction start
- Jun 2, 2026(forecast)
- Construction end
- Nov 30, 2026(forecast)