Salt Spring Island - Grow Together
Salt Spring Island, British Columbia
Federal contribution
$31,000
Federal share50%
of $62.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20222023202420252026
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Salt Spring Island Farmland Trust Society
- Construction start
- Oct 5, 2024(actual)
- Construction end
- Nov 15, 2025(actual)
Against the original forecast
- Construction start10 months lateforecast Nov 30, 2023
- Construction end7 weeks earlyforecast Dec 31, 2025