Back to projects

Shawnigan Lake - The Expansion of the Shawnigan Lake Museum

Cowichan Valley, British Columbia

completeCultureRNIS
Federal contribution
$718,602
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
2022202320242025
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 24, 2023(actual)
Construction end
Feb 28, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 15, 2023
  • Construction end2 months lateforecast Dec 15, 2024

Also in Cowichan Valley