Back to projects

BC Hydro Customer Connection Project: Cowichan District Hospital Electrification

Cowichan Valley, British Columbia

completeGreen EnergyGIS
Federal contribution
$1.2M
$1,181,786
Federal share50%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2025
20242025
Built

Approved 17 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 15, 2024(actual)
Construction end
Sep 9, 2025(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 1, 2024
  • Construction end3 months earlyforecast Dec 1, 2025

Also in Cowichan Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67745 in the federal list. How to read these figures.