Penticton - Electric Vehicle Rapid Charging Infrastructure
Federal contribution
$134,761
Federal share40%
of $336.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2022
20222023202420252026
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Penticton
- Construction start
- Nov 4, 2024(actual)
- Construction end
- Jan 30, 2026(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 3, 2024
- Construction end2 months earlyforecast Mar 31, 2026
Also in Penticton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62093 in the federal list. How to read these figures.