Antigonish Community Transit Society Fixed Bus Route, Upgrading Services, Antigonish, Nova Scotia
Federal contribution
$17,500
Federal share100%
of $17.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 21, 2023
2023
Built
Approved 11 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Antigonish Community Transit Society
- Construction start
- Sep 15, 2022(actual)
- Construction end
- Jun 30, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Feb 1, 2022
- Construction end12 months lateforecast Jun 30, 2022
Also in Antigonish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62146 in the federal list. How to read these figures.