Antigonish Community Transit Society Fixed Bus Route, Upgrading Services, Antigonish, Nova Scotia

Antigonish, Nova Scotia

completeCapacity BuildingRTSF
Federal contribution
$17,500
Federal share100%

of $17.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 21, 2023
2023
Built

Approved 11 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Sep 15, 2022(actual)
Construction end
Jun 30, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast Feb 1, 2022
  • Construction end12 months lateforecast Jun 30, 2022

Also in Antigonish