Create a multi-step plan to address the community's transit needs for future transit delivery in MRC de Portneuf.

Portneuf, Quebec

completeCapacity BuildingRTSF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 5, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
RM of Portneuf
Construction start
Dec 1, 2022(actual)
Construction end
Jun 30, 2024(actual)

Against the original forecast

  • Construction start11 months lateforecast Jan 1, 2022
  • Construction end16 months lateforecast Feb 28, 2023

Also in Portneuf

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62156 in the federal list. How to read these figures.