completeDrinking WaterCWWF
Federal contribution
$1.3M
$1,319,667
Federal share50%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
201720182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Portneuf
Construction start
Sep 28, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2017
  • Construction end7 months earlyforecast Nov 1, 2019