Birtle Sanitary Sewer and Water Main Rehabilitation

Prairie View, Manitoba

underwayDrinking WaterGIS
Federal contribution
$855,632
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2022
20222023202420252026
BuiltForecast

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 16, 2024(actual)
Construction end
Jul 31, 2026(forecast)

Against the original forecast

  • Construction start2.6 years lateforecast Feb 9, 2022

Also in Prairie View

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62167 in the federal list. How to read these figures.