Municipal Well and Network
Federal contribution
$2.0M
$2,000,000
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2017
20182019
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Prairie View
- Construction start
- Nov 30, 2017(actual)
- Construction end
- Jul 19, 2019(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 30, 2017
- Construction end4 months lateforecast Mar 22, 2019
Also in Prairie View
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49301 in the federal list. How to read these figures.