Municipal Well and Network

Prairie View, Manitoba

completeDrinking WaterCWWF
Federal contribution
$2.0M
$2,000,000
Federal share50%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
20182019
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 30, 2017(actual)
Construction end
Jul 19, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 30, 2017
  • Construction end4 months lateforecast Mar 22, 2019