Choices for Youth social enterprise and Innovation Hub
St. John's, Newfoundland and Labrador
Federal contribution
$2.3M
$2,310,815
Federal share63%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2024
2022202320242025
Built
Approved 2.1 years before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Choices for Youth
- Construction start
- Aug 4, 2023(actual)
- Construction end
- Nov 20, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2023
- Construction end7 months lateforecast Apr 30, 2024
Also in St. John's