Ituna Arena Retrofit
Federal contribution
$2.4M
$2,398,653
Federal share80%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 7, 2022
202220232024
Built
Approved 9 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Ituna Community Arena Cooperative
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Jan 31, 2024(actual)
Against the original forecast
- Construction start10 months earlyforecast Apr 1, 2022
- Construction end13 months lateforecast Dec 31, 2022
Also in Ituna
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62313 in the federal list. How to read these figures.