Lagoon Upgrades

Ituna, Saskatchewan

completeWastewaterCWWF
Federal contribution
$65,000
Federal share50%

of $130.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2017
20172018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Ituna
Construction start
Jun 1, 2017(actual)
Construction end
Dec 22, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 15, 2017
  • Construction end3 weeks lateforecast Nov 30, 2017

Also in Ituna

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48458 in the federal list. How to read these figures.