Station Road Erosion Control

Placentia, Newfoundland and Labrador

completeDisaster MitigationGIS
Federal contribution
$231,936
Federal share40%

of $579.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
2022202320242025
Built

Approved 3 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Placentia
Construction start
May 15, 2024(actual)
Construction end
Nov 15, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 15, 2024
  • Construction end7 months earlyforecast Jun 18, 2025

Also in Placentia

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62347 in the federal list. How to read these figures.