Station Road Erosion Control
Placentia, Newfoundland and Labrador
Federal contribution
$231,936
Federal share40%
of $579.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
2022202320242025
Built
Approved 3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Placentia
- Construction start
- May 15, 2024(actual)
- Construction end
- Nov 15, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 15, 2024
- Construction end7 months earlyforecast Jun 18, 2025
Also in Placentia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62347 in the federal list. How to read these figures.