Construction of Gorillas Park in the Rosemont La-Petite-Patrie borough of Montreal
Federal contribution
$2.2M
$2,166,534
Federal share37%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2025
2023202420252026
Built
Approved 3.4 years before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Ville de Montréal - Service de l'urbanisme et de la mobilité
- Construction start
- Jan 26, 2023(actual)
- Construction end
- Aug 29, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Sep 1, 2022
- Construction end9 months lateforecast Nov 15, 2023