Vehicle Acquisition (Phase 8)
Federal contribution
$8.7M
$8,659,806
Federal share40%
of $21.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 27, 2022
202320242025
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- Dec 31, 2022(actual)
- Construction end
- Jun 1, 2025(actual)
Against the original forecast
- Construction end3 months lateforecast Mar 1, 2025
Also in Undefined
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62649 in the federal list. How to read these figures.