Back to projects

Berens River Road Upgrades - Federal Roads Component

Berens River, Manitoba

underwayHighways and RoadsRNIS
Federal contribution
$10.7M
$10,650,000
Federal share75%

of $14.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 27, 2022
today
202220232024202520262027
BuiltForecast

Approved 8 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Berens River First Nation
Construction start
Jul 10, 2025(actual)
Construction end
Oct 31, 2026(forecast)

Against the original forecast

  • Construction start5 months lateforecast Feb 12, 2025

Also in Berens River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62691 in the federal list. How to read these figures.