Federal contribution
$5.6M
$5,625,000
Federal share75%

of $7.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 27, 2022
today
2022202420262028
BuiltForecast

Approved 7 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Berens River First Nation
Construction start
May 16, 2026(forecast)
Construction end
Dec 31, 2028(forecast)