Improvements to the Township of North Dundas Drinking Water System
Federal contribution
$2.0M
$1,999,864
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023202420252026
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of North Dundas
- Construction start
- Oct 10, 2023(actual)
- Construction end
- Apr 30, 2026(forecast)
Also in North Dundas
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62801 in the federal list. How to read these figures.