Back to projects

Improvements to the Township of North Dundas Drinking Water System

North Dundas, Ontario

underwayDrinking WaterGIS
Federal contribution
$2.0M
$1,999,864
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023202420252026
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of North Dundas
Construction start
Oct 10, 2023(actual)
Construction end
Apr 30, 2026(forecast)

Also in North Dundas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62801 in the federal list. How to read these figures.