Back to projects

Rehabilitation to 70 Emma Street Sewage Pumping Station Building including structural, electrical and mechanical elements

North Dundas, Ontario

completeWastewaterCWWF
Federal contribution
$65,993
Federal share47%

of $141.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of North Dundas
Construction start
Oct 16, 2017(actual)
Construction end
Dec 10, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017
  • Construction end2 months lateforecast Sep 30, 2019

Also in North Dundas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49078 in the federal list. How to read these figures.