MAB/Mackay Centre Boiler Room Upgrade
Federal contribution
$483,199
Federal share80%
of $604.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
20232024
Built
Approved 2.5 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du Centre-Ouest-de-l'Île-de-Montréal
- Construction start
- Apr 11, 2022(actual)
- Construction end
- Nov 22, 2023(actual)
Against the original forecast
- Construction start6 months earlyforecast Oct 4, 2022
- Construction end8 months lateforecast Mar 31, 2023
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62836 in the federal list. How to read these figures.