MAB/Mackay Centre Boiler Room Upgrade

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$483,199
Federal share80%

of $604.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2024
20232024
Built

Approved 2.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 11, 2022(actual)
Construction end
Nov 22, 2023(actual)

Against the original forecast

  • Construction start6 months earlyforecast Oct 4, 2022
  • Construction end8 months lateforecast Mar 31, 2023

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62836 in the federal list. How to read these figures.