Roy Street West Watermain Upgrade
Federal contribution
$372,500
Federal share40%
of $931.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
202320242025
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Laurentian Valley
- Construction start
- Apr 1, 2024(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 1, 2024
Also in Laurentian Valley
- Rehabilitation of Bruham Avenue Watermain$96.7K
- Laurentian Valley Multi-Use Trail Enhancements$80.0K
- Laurentian Valley Active Transportation & Trails Plan$50.0K
- Detailed Design for the Reconstruction of Roy Street Water, Wastewater and Stormwater infrastructure$50.0K
- Township of Laurentian Valley Asset Management$4.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62923 in the federal list. How to read these figures.