Detailed Design for the Reconstruction of Roy Street Water, Wastewater and Stormwater infrastructure

Laurentian Valley, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share26%

of $195.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 30, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction end2 months lateforecast Oct 31, 2018

Also in Laurentian Valley