Hamilton Street Watermain Replacement

Arran-Elderslie, Ontario

completeDrinking WaterGIS
Federal contribution
$170,400
Federal share40%

of $426.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
20232024
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
May 8, 2023(actual)
Construction end
Dec 15, 2023(actual)

Against the original forecast

  • Construction end2 months lateforecast Sep 30, 2023

Also in Arran-Elderslie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62944 in the federal list. How to read these figures.