Hamilton Street Watermain Replacement
Federal contribution
$170,400
Federal share40%
of $426.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
20232024
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Arran-Elderslie
- Construction start
- May 8, 2023(actual)
- Construction end
- Dec 15, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Sep 30, 2023
Also in Arran-Elderslie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62944 in the federal list. How to read these figures.