Upgrade to Watermain, Sanitary and Storm Sewer and Road restoration
Federal contribution
$174,307
Federal share26%
of $671.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Arran-Elderslie
- Construction start
- May 2, 2017(actual)
- Construction end
- Sep 30, 2017(actual)