Nackawic - North Side Wastewater Treatment Facility Rehabilitation
Federal contribution
$313,344
Federal share40%
of $783.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 8, 2023
2023202420252026
BuiltForecast
Approved 13 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Nackawic
- Construction start
- Nov 9, 2023(actual)
- Construction end
- Jun 30, 2026(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Oct 1, 2023
Also in Nackawic
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63171 in the federal list. How to read these figures.