Harding Drive and Landegger Drive - Storm and Sanitary Pipe Re-lining
Federal contribution
$226,996
Federal share50%
of $454.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Nackawic
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Nov 16, 2018(actual)
Against the original forecast
- Construction end11 months lateforecast Dec 1, 2017
Also in Nackawic