Omemee Trail
Federal contribution
$98,840
Federal share60%
of $164.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2023
2023
Built
Approved 7 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Kawartha Trans Canada Trail Association
- Construction start
- Apr 4, 2023(actual)
- Construction end
- May 25, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 8, 2022
Also in Kawartha Lakes
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63192 in the federal list. How to read these figures.