underwayPublic TransitPTIS
Federal contribution
$17.5M
$17,498,000
Federal share50%

of $35.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2023
today
202320242025202620272028
BuiltForecast

Approved 13 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Jan 2, 2024(actual)
Construction end
Aug 28, 2028(forecast)

Against the original forecast

  • Construction start5 weeks lateforecast Dec 1, 2023

Also in Metro Vancouver