Back to projects

SkyTrain Traction Power Replacement

Metro Vancouver, British Columbia

underwayPublic TransitPTIS
Federal contribution
$10.1M
$10,113,000
Federal share50%

of $20.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2025
today
202420252026202720282029
BuiltForecast

Approved 2.4 years before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Mar 28, 2025(actual)
Construction end
Mar 31, 2029(forecast)

Also in Metro Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67250 in the federal list. How to read these figures.