Wakefield Lift Station Replacement and Capacity Expansion
Federal contribution
$365,715
Federal share40%
of $914.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 16, 2022
2023202420252026
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District of Sechelt
- Construction start
- Jul 25, 2023(actual)
- Construction end
- Dec 12, 2025(actual)
Against the original forecast
- Construction end6 months lateforecast Jun 5, 2025
Also in Sechelt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63385 in the federal list. How to read these figures.