Regional Trail Network - Connecting coastal communities
Channel-Port aux Basques, Newfoundland and Labrador
Federal contribution
$27,949
Federal share89%
of $31.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.6 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Channel-Port aux Basques
- Construction start
- Jun 29, 2022(actual)
- Construction end
- Jul 30, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 31, 2022
- Construction end7 months lateforecast Dec 30, 2022
Also in Channel-Port aux Basques
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63447 in the federal list. How to read these figures.