Transit Buses 2022
Federal contribution
$909,205
Federal share75%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 22, 2023
2023
Built
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Whitehorse
- Construction start
- May 13, 2022(actual)
- Construction end
- May 31, 2023(actual)
Against the original forecast
- Construction end2 months earlyforecast Jul 30, 2023
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63465 in the federal list. How to read these figures.