Back to projects

Ventilation Improvements in Schools

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$6.1M
$6,078,032
Federal share80%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2024
20232024
Built

Approved 2.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 29, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast May 20, 2022

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63509 in the federal list. How to read these figures.